Article 56 – National transition to fibre plan

Part V
Transition to fibre, markets functioning and competition
Title I
Transition to fibre networks

Commission proposal 21 January 2026 · COM(2026) 16 final

  1. 1.

    By 31 October 2029, each Member State shall prepare a transition to fibre plan and notify it to the Commission.

  2. 2.

    The transition to fibre plan shall set out the Member State’s strategy for the nationwide transition to fibre networks, in particular for the migration from copper to FTTH networks. It shall contain the following information:

    1. (a)

      information on the coverage of copper and fibre networks;

    2. (b)

      a description of measures in place or planned to foster fibre deployment and the transition to FTTH networks;

    3. (c)

      a list of CSO areas indicating, for each area, whether the sustainability conditions set out in Article 57(1) are met, together with the corresponding migration milestones and, where relevant, enabling measures.

  3. 3.

    By 30 June 2034, Member States shall update their transition to fibre plan and notify the updated plan to the Commission.

  4. 4.

    The updated transition to fibre plan shall report progress on the implementation of the initial plan. It shall contain the following information:

    1. (a)

      information on the status of the copper switch-off in each CSO area;

    2. (b)

      a list of CSO areas where fibre deployment is economically viable but will only be completed after 31 December 2035, together with information on the availability of adequate connectivity solutions capable of replacing copper-based services;

    3. (c)

      a list of CSO areas where fibre deployment is not economically viable.

  5. 5.

    The Commission may comment on the initial and the updated transition to fibre plan within one month from its receipt. Member States shall take account of those comments.

Parliament amendments

ITRE draft report 20 October 2026

  1. 365 Alternative Michał KoboskoRapporteur · ITRE “By 12 months after the entry into force of this Regulation, each Member State shall prepare a transition to fibre plan and notify it to the…” Article 56 – paragraph 1

    Text proposed by the Commission

    1.By 31 October 2029, each Member State shall prepare a transition to fibre plan and notify it to the Commission.

    Amendment

    1.By 12 months after the entry into force of this Regulation, each Member State shall prepare a transition to fibre plan and notify it to the Commission.

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 1
  2. 366 Alternative Michał KoboskoRapporteur · ITRE “The transition to fibre plan shall set out the Member State’s strategy for the nationwide transition to fibre networks, in particular for the…” Article 56 – paragraph 2 – introductory part

    Text proposed by the Commission

    2.The transition to fibre plan shall set out the Member State’s strategy for the nationwide transition to fibre networks, in particular for the migration from copper to FTTH networks. It shall contain the following information:

    Amendment

    2.The transition to fibre plan shall set out the Member State’s strategy for the nationwide transition to fibre networks, in particular for the migration from copper to FTTH networks. It shall contain, in particular, a description of measures in place or planned to foster fibre deployment and the transition to FTTH networks.

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 2 – introductory part
  3. 367 Deletion Michał KoboskoRapporteur · ITRE Deletes the Commission’s wording Article 56 – paragraph 2 – point a

    Text proposed by the Commission

    (a)information on the coverage of copper and fibre networks;

    Amendment

    deleted

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 2 – point a
  4. 368 Deletion Michał KoboskoRapporteur · ITRE Deletes the Commission’s wording Article 56 – paragraph 2 – point b

    Text proposed by the Commission

    (b)a description of measures in place or planned to foster fibre deployment and the transition to FTTH networks;

    Amendment

    deleted

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 2 – point b
  5. 369 Deletion Michał KoboskoRapporteur · ITRE Deletes the Commission’s wording Article 56 – paragraph 2 – point c

    Text proposed by the Commission

    (c)a list of CSO areas indicating, for each area, whether the sustainability conditions set out in Article 57(1) are met, together with the corresponding migration milestones and, where relevant, enabling measures.

    Amendment

    deleted

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 2 – point c
  6. 370 Alternative Michał KoboskoRapporteur · ITRE “By 72 months after the entry into force of this Regulation, Member States shall update their transition to fibre plan and notify the updated plan to…” Article 56 – paragraph 3

    Text proposed by the Commission

    3.By 30 June 2034, Member States shall update their transition to fibre plan and notify the updated plan to the Commission.

    Amendment

    3.By 72 months after the entry into force of this Regulation, Member States shall update their transition to fibre plan and notify the updated plan to the Commission. The updated transition to fibre plan shall report progress on the implementation of the initial plan. It shall also contain the information on the status of the copper switch-off in each CSO area.

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 3
  7. 371 Deletion Michał KoboskoRapporteur · ITRE Deletes the Commission’s wording Article 56 – paragraph 4

    Text proposed by the Commission

    4.The updated transition to fibre plan shall report progress on the implementation of the initial plan. It shall contain the following information:

    (a)information on the status of the copper switch-off in each CSO area;

    (b)a list of CSO areas where fibre deployment is economically viable but will only be completed after 31 December 2035, together with information on the availability of adequate connectivity solutions capable of replacing copper-based services;

    (c)a list of CSO areas where fibre deployment is not economically viable.

    Amendment

    deleted

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 4
  8. 372 Alternative Michał KoboskoRapporteur · ITRE “The Commission may comment on the initial and the updated transition to fibre plan, and propose amendments, within one month from its receipt. Member…” Article 56 – paragraph 5

    Text proposed by the Commission

    5.The Commission may comment on the initial and the updated transition to fibre plan within one month from its receipt. Member States shall take account of those comments.

    Amendment

    5.The Commission may comment on the initial and the updated transition to fibre plan, and propose amendments, within one month from its receipt. Member States shall take account of those inputs.

    Rapporteur
    Michał Kobosko
    Group
    Rapporteur
    Targets
    Article 56
    Document
    ITRE draft report
    Printed header
    Article 56 – paragraph 5