ITRE–IMCO Amendment 139

Article 13 – paragraph 2

Document
ITRE–IMCO draft report
Rapporteurs
Diego Solier and Reinier Van Lanschot
  1. 139 Alternative Diego Solier +1Rapporteurs · ITRE–IMCO “For each designated acceleration zone, on the basis of the impact analysis referred to in Article 10 (1), Member States shall prepare and issue an…” Article 13 – paragraph 2

    Text proposed by the Commission

    2.For each designated acceleration zone, Member States shall prepare and issue an aggregated baseline permit authorising the deployment of data centres in that acceleration zone. This aggregated baseline permit shall cover the permits and administrative authorisations required for the data centre projects located within the acceleration zone, excluding installation-specific permits.

    Amendment

    2.For each designated acceleration zone, on the basis of the impact analysis referred to in Article 10 (1), Member States shall prepare and issue an aggregated baseline permit authorising the deployment of data centres in that acceleration zone. This aggregated baseline permit shall cover the permits and administrative authorisations required for the data centre projects located within the acceleration zone, excluding installation-specific permits.

    Rapporteurs
    Diego Solier and Reinier Van Lanschot
    Group
    Rapporteurs
    Targets
    Article 13
    Document
    ITRE–IMCO draft report
    Printed header
    Article 13 – paragraph 2

Cite

Amendment 139 (draft report by Diego Solier and Reinier Van Lanschot), European Parliament, Committee on Industry, Research and Energy and Committee on the Internal Market and Consumer Protection, draft report on COM(2026) 502 (CJ18-PR-797430, PE797.430v02-00, 17 November 2026), pp. 95–96