ITRE–IMCO Amendment 117

Article 10 – paragraph 3 b (new)

Document
ITRE–IMCO draft report
Rapporteurs
Diego Solier and Reinier Van Lanschot
  1. 117 Addition Diego Solier +1Rapporteurs · ITRE–IMCO “Anti-speculation milestones relating to the reservation of electricity grid capacity shall be public, verifiable and proportionate to the scale of…” Article 10 – paragraph 3 b (new)

    Text proposed by the Commission

    Nothing printed in this column.

    Amendment

    3b.Anti-speculation milestones relating to the reservation of electricity grid capacity shall be public, verifiable and proportionate to the scale of the project. Before releasing a reservation for failure to meet the 18 months deadline, the competent authority shall give the holder an opportunity to be heard and shall take account of delays attributable to public authorities, the grid operator or force majeure. Release shall be carried out in accordance with applicable grid access and connection rules.

    Rapporteurs
    Diego Solier and Reinier Van Lanschot
    Group
    Rapporteurs
    Targets
    Article 10
    Document
    ITRE–IMCO draft report
    Printed header
    Article 10 – paragraph 3 b (new)

Cite

Amendment 117 (draft report by Diego Solier and Reinier Van Lanschot), European Parliament, Committee on Industry, Research and Energy and Committee on the Internal Market and Consumer Protection, draft report on COM(2026) 502 (CJ18-PR-797430, PE797.430v02-00, 17 November 2026), pp. 83–84

https://research.eutechreg.com/trackers/cada/amendments/itre-imco-117/