ITRE–IMCO Amendment 114
Article 10 – paragraph 2 – point a
114 ~Alternative Diego Solier +1Rapporteurs · ITRE–IMCO “review every year current and future acceleration zones, and assess the impact based on the analysis mentioned in paragraph 1 regarding the energy…” Article 10 – paragraph 2 – point a
Text proposed by the Commission
(a)conduct, and review at least every three years, a comprehensive analysis of the energy needs and their respective impacts on greenhouse gas emissions, of current and future acceleration zones and identify the required energy infrastructure capacity for the proper functioning and development of data centre projects located in the acceleration zones. Such analysis shall be conducted, at least, when designating the acceleration zones pursuant to paragraph 1;
Amendment
(a)review every year current and future acceleration zones, and assess the impact based on the analysis mentioned in paragraph 1 regarding the energy needs and their respective impacts on greenhouse gas emissions, the impact on air, noise and water pollution and identify the required energy and water infrastructure capacity and use for the proper functioning and development of data centre projects located in the acceleration zones. Member States shall also review the social and economic impacts of those data centres, including on public health, employment and tax revenue.
- Rapporteurs
- Diego Solier and Reinier Van Lanschot
- Group
- Rapporteurs
- Targets
- Article 10
- Document
- ITRE–IMCO draft report
- Source
- Official text, page 82
- Printed header
- Article 10 – paragraph 2 – point a
Cite
Amendment 114 (draft report by Diego Solier and Reinier Van Lanschot), European Parliament, Committee on Industry, Research and Energy and Committee on the Internal Market and Consumer Protection, draft report on COM(2026) 502 (CJ18-PR-797430, PE797.430v02-00, 17 November 2026), p. 82