  1. 1.

    Operators shall draw up one or more copper switch-off plans for the CSO areas where the copper switch-off is mandated. The plan shall include timelines, technical measures, communication activities and arrangements for the migration of access seekers and end-users.

  2. 2.

    Operators shall submit their copper switch-off plans to the national regulatory authority within six months of the adoption of the binding legal act pursuant to Article 54(4).

  3. 3.

    The national regulatory authority shall assess the plans within two months from their receipt and shall either approve them or approve them subject to amendments.

  4. 4.

    Operators shall implement the copper switch-off plans as approved by the national regulatory authority, including any amendments requested. Operators shall report progress to the national regulatory authority at intervals determined by it.